Is the shop ready for the machine?

A machine can match the work, budget and production plan while the facility remains unprepared for delivery. Organize the complete route from machine identity through production-ready acceptance before the truck moves.

Version 1.0October 20269.5 MB PDFIndependent research
Machine Blue Book Machine Readiness Worksheet cover with a precision CNC machining center.

The five-minute screen

Before paying a deposit or scheduling freight, answer these ten questions.

Question Confirmed Needs work Owner
Is the exact machine identity and configuration documented? ☐ ☐
Will the machine fit through every door, turn, and aisle? ☐ ☐
Is the floor or foundation suitable for the loaded machine? ☐ ☐
Does the facility have the required voltage, phase, frequency, and capacity? ☐ ☐
Are transformer or phase-conversion needs resolved? ☐ ☐
Are compressed air, coolant, mist, exhaust, water, and drainage requirements known? ☐ ☐
Is the freight, permit, unloading, and rigging scope written? ☐ ☐
Are installation, leveling, startup, and acceptance responsibilities assigned? ☐ ☐
Are tooling, workholding, inspection, software, and programs ready? ☐ ☐
Are operators, maintenance staff, service support, and safety procedures ready? ☐ ☐

If any answer is unknown, the machine may still be a good purchase. The unknown simply belongs in the plan and budget before it becomes a surprise.


1. Identify the exact machine

Record information from the nameplate, control, option list, maintenance records, and seller documentation.

  • Manufacturer:
  • Model:
  • Serial number:
  • Year of manufacture:
  • Control manufacturer and generation:
  • Spindle configuration:
  • Axis travels:
  • Table, chuck, or work-envelope dimensions:
  • Tool capacity and taper:
  • Included options:
  • Included accessories:
  • Included tooling and workholding:
  • Current location:
  • Operating status:

Evidence to retain

  • ☐ Nameplate photograph
  • ☐ Control power-on photograph
  • ☐ Serial number photograph
  • ☐ Option sheet or build sheet
  • ☐ Maintenance and service history
  • ☐ Video of operation when available
  • ☐ Alarm screen or diagnostic information
  • ☐ Written list of everything included and excluded

Start with the MBB machine buying guide and machine identity and options guide.


2. Map the physical route

The machine footprint is not the same as the move-in envelope.

Measure:

  • Machine width, depth, height, and shipping weight
  • Crate, pallet, skid, or shipping-brace dimensions
  • Door width and height
  • Dock height and capacity
  • Overhead clearance
  • Aisle width
  • Turning radius
  • Floor transitions, ramps, pits, and drains
  • Crane, gantry, forklift, or toe-jack access
  • Final service-clearance area

Route notes

  • Tightest width:
  • Tightest height:
  • Sharpest turn:
  • Floor obstacle:
  • Required temporary removal:
  • Final maintenance clearance:

Use the footprint, layout, and access guide before the rigger arrives.


3. Confirm the floor and foundation

Do not assume an industrial floor is automatically suitable for every machine.

Confirm with the machine documentation and qualified professionals:

  • Loaded machine weight and center of gravity
  • Number and location of leveling points
  • Point loads and vibration considerations
  • Slab thickness and reinforcement information when available
  • Anchor requirements
  • Isolation-pad or foundation requirements
  • Pit, trench, drainage, or coolant-containment needs
  • Clearance for doors, guards, conveyors, and maintenance panels

Decision record

  • Documentation reviewed by:
  • Foundation or floor work required:
  • Work completed by:
  • Completion date:
  • Open issue:

Read the foundation and floor-loading guide.


4. Verify electrical readiness

Capture the machine nameplate. Do not estimate facility compatibility from horsepower alone.

Record:

  • Required voltage:
  • Phase:
  • Frequency:
  • Full-load current or rated current:
  • Recommended disconnect or protective-device information:
  • Transformer requirement:
  • Phase-converter requirement:
  • Facility service voltage:
  • Available capacity:
  • Disconnect location:
  • Conductor path and length:

Electrical design, installation, and verification belong to qualified professionals and applicable codes. MBB provides planning references, not electrical engineering services.

Use the machine electrical reference, nameplate-data guide, and facility-power planning guide.


5. Confirm supporting utilities

Utility Requirement Existing capacity Work required Owner
Compressed air
Coolant
Mist collection
Exhaust
Process water
Drainage
Chiller
Hydraulic support
Chip handling
Network connection

Read the air, coolant, mist, and utilities guide.


6. Define freight and rigging in writing

The quote should identify more than a total price.

Confirm:

  • Pickup location and access conditions
  • Seller's loading responsibility
  • Blocking, bracing, wrapping, and weather protection
  • Carrier and trailer type
  • Oversize or overweight permit responsibility
  • Route restrictions and appointment requirements
  • Cargo, rigging, and liability insurance documentation
  • Delivery location and site conditions
  • Unloading equipment and lift plan
  • Placement, leveling, anchoring, and cleanup
  • Damage documentation and claim process
  • Cancellation, delay, standby, and change-order terms

Required contacts

  • Seller contact:
  • Carrier contact:
  • Rigger contact:
  • Insurance contact:
  • Facility contact:
  • Delivery appointment:

Use the freight, permit, and rigging guide and machine rigging directory.


7. Define installation and acceptance

Write down who performs each task.

Task Responsible party Date Evidence
Unload and place
Level and anchor
Electrical connection
Air and utility connection
Fluid fill and preparation
OEM or technician startup
Geometry or calibration check
Safety verification
Test cut or run-off
Acceptance signoff

Define the acceptance test before delivery. The buyer and seller should know what condition, performance, documentation, and included items complete the transaction.

Read the installation, commissioning, and acceptance guide.


8. Prepare production support

  • ☐ Toolholders and retention knobs
  • ☐ Cutting tools and inserts
  • ☐ Chucks, jaws, vises, fixtures, and workholding
  • ☐ Probes, setters, and calibration artifacts
  • ☐ Inspection equipment
  • ☐ CAM postprocessor
  • ☐ Program-transfer method
  • ☐ Networking and backups
  • ☐ Coolant and filtration supplies
  • ☐ Lubricants and maintenance consumables
  • ☐ Critical spare parts
  • ☐ Service contacts
  • ☐ Operator training
  • ☐ Maintenance training
  • ☐ Safety procedures

Use the tooling, workholding, and inspection guide.


9. Calculate the installed decision

Cost category Estimate Confirmed quote Final
Machine purchase
Taxes and transaction costs
Inspection
Freight
Permits and escorts
Rigging
Foundation or floor work
Electrical work
Utilities and extraction
Tooling and workholding
Software and postprocessor
Installation and calibration
Training
Initial maintenance and spares
Contingency
Total installed estimate

The purchase price is one line in the decision. Use the total installed cost guide.


Final readiness decision

  • ☐ Ready to schedule pickup
  • ☐ Ready after listed actions are completed
  • ☐ Hold shipment pending information
  • ☐ Re-evaluate the purchase

Open actions:

Decision owner:

Target completion date:


Independent-use notice

The Machine Blue Book is an independent educational and reference resource. It is not the seller, broker, lender, carrier, rigger, engineer, electrician, inspector, attorney, insurer, or OEM for equipment described or linked through the site. Verify machine availability, condition, specifications, requirements, pricing, contracts, licensing, insurance, and site suitability directly with the responsible parties and qualified professionals.