Freeze the shipped configuration, loaded vehicle, route, custody and final-placement scope before the machine moves.
A machine move is a chain of custody.
The seller, origin rigger, carrier, broker, permit service, escorts, destination rigger and installer may be different parties. Assign each handoff, condition record and risk before pickup.
Facts to establish
- Machine shipping dimensions, weight, center of gravity and lift points
- Removed components, fluids, blocking, bracing, covers and packing
- Origin loading access, equipment and party responsible
- Carrier identity, authority, cargo protection, trailer and securement
- Final loaded dimensions, weights, route, permits and escorts
- Destination unloading, building path, placement and acceptance
Documents and deliverables
- Machine condition and serial record before disconnection
- Rigging scope and lift or handling plan
- Carrier, broker and insurance verification
- Bill of lading and declared-value instructions
- Permit and route package for the actual configuration
- Delivery exceptions, photographs and custody signoffs
What happens in a site survey?
A site survey checks every point between where the machine sits and where it will sit. The Fabricator lists the basics: "you need to know the dimensions of the doors, floors, and ceiling height," along with headroom, and whether there are floor pits or openings along the route [1]. An industrial contractor's checklist asks "What are the weights and dimensions of the equipment and its components being relocated?" [2]
Gather "electrical diagrams, mechanical drawings with weights and dimensions, and foundation specifications" first [1]; the builder's installation manual is the best single source for weight, lifting points and foundation requirements. Check door, aisle and ceiling clearances, floor pits and drains, overhead obstructions (lights, sprinklers, crane rails, ductwork), truck access, and the utility drops at the new site.
Can the floor carry the machine?
This is an engineering question for a licensed engineer. Two loads matter: the route, where "Will the floors hold the weight of the equipment being moved and the rigging equipment?" [1], and the final position [2]. For dedicated foundations, Okuma America's Gary Snow advises: "Hire a licensed engineer to test the sub soil conditions at the foundation site"; "Concrete construction should be of a single pour"; "Use a quality concrete that is rated at 5000 lb./in.² resistance"; "Always isolate your foundation from other elements with a Styrofoam isolation barrier"; and "Never connect your foundation to existing building foundations" [3]. Those are one builder's general recommendations; your machine's own foundation drawing governs.
FANUC's ROBODRILL catalog notes floor fastening "may be required," including "to prevent the machine from toppling over due to an earthquake." [4] See foundation and floor loading.
Compiled by Bronto, our AI research assistant, from the sources listed on this page; checked against them. How we make these pages.
Ask before the decision becomes expensive.
A useful answer identifies a person, document, number, date, scope or acceptance test. Replace assumptions with evidence.
Who physically touches the machine?
Name the legal entity and crew for disconnect, loading, transport, unloading and placement—not only the coordinator.
What does the freight price exclude?
Ask about permits, escorts, tarps, crating, transloading, detention, storage, loading and final placement.
What protection responds to damage?
Separate regulatory liability filings, cargo coverage, riggers liability, declared value, exclusions and contractual limits.
When does risk transfer?
Put custody, inspection, exceptions, claims notice and acceptance in the transaction and transportation documents.
What insurance covers a machine move?
IRMI explains that riggers liability insurance "covers a contractor's liability arising out of the moving of property and equipment that belongs to others," and that the standard CGL policy "does not cover this risk due to the exclusion for personal property of others in your care, custody, or control" [5]. Travelers adds that "relying on even the best general liability (GL) insurance may not be enough," describes rigger's legal liability coverage for property "owned by another party" in the contractor's care, and describes installation floaters for equipment held before installation [6].
Ask the rigger: do you carry riggers liability or rigger's legal liability coverage, and with what limits? Does it cover lifting, transport, storage and setting? Can my company be an additional insured? Will you send a certificate before the job? Then ask your own insurer whether your property policy covers the machine in transit, and from when.
How is the lift planned?
Brookhaven National Laboratory's Basic Rigging Workbook requires the rigger to "Determine and identify the location of the load's center of gravity" before a lift, and lists weight, center of gravity, lift points, crane capacity and sling angles among the items to confirm [7]. Its sling angle factors are 1.000 at 90 degrees, 1.155 at 60, 1.414 at 45 and 2.000 at 30, with the advice "Avoid rigging loads where angle is less than 45°." [7]
OSHA's sling standard for general industry requires that "Each day before being used, the sling and all fastenings and attachments shall be inspected for damage or defects by a competent person designated by the employer," that damaged slings be removed from service, that slings "shall not be loaded in excess of their rated capacities," and that "All employees shall be kept clear of loads about to be lifted and of suspended loads." [8] Use the builder's designated lifting points; never improvise lift points on castings or sheet metal.
How is the machine leveled and recommissioned?
- Set and level to the builder's procedure. Published procedures such as TRAK's TC820si guide level at the corner screws first, check along the axis travel and for twist, then bring the center screws into light contact [9].
- Anchor and grout if the foundation drawing calls for it [3][4].
- Have the electrician verify supply voltage and phase against the builder's specification before power-up.
- Check geometry. Renishaw describes a manufacturer planning "subsequent checks for geometry, ballscrew accuracy and backlash issues" after a move [10]; a ballbar test before and after gives a direct comparison.
- Warm up the spindle, run test cuts, and confirm parts meet print before production.
Pause when the scope is vague.
- Freight quote based on catalog weight rather than shipped configuration
- Unknown carrier until dispatch
- No condition photographs at custody changes
- Rigging, loading or unloading assumed but not written
- Declared value and claim limitations not reviewed
What a controlled file contains.
- Shipped-configuration inventory
- Provider and insurance due diligence
- Issued permit and route package
- Condition photographs at every handoff
- Delivery and placement acceptance
Use the source that controls the question.
These links provide a starting point. The exact machine, agreement, site, jurisdiction and qualified professionals control the final decision.
- FHWA state oversize permit contacts ↗
- FMCSA SAFER Company Snapshot ↗
- MBB transport and permit library ↗
- [1] Steve Richardson, "How to Make the Most of a Press Move," The Fabricator, June 9, 2009 ↗ (accessed November 9, 2026)
- [2] Lee Contracting, "Part 1: Planning a Press Move," November 30, 2017 ↗ (accessed November 9, 2026)
- [3] Gary Snow (Okuma America), "'Foundations' for Machine Tool Success," March 26, 2014 ↗ (accessed November 9, 2026)
- [4] FANUC, ROBODRILL α-DiB5ADV catalog, RDRILLA-DiB5ADV(E)-03b, 2021.10 ↗ (accessed November 9, 2026)
- [5] IRMI, "Riggers Liability Insurance" ↗ (accessed November 9, 2026)
- [6] Travelers, "Millwright Accidents, Safety Risks and Insurance Gaps," November 21, 2023 ↗ (accessed November 9, 2026)
- [7] Brookhaven National Laboratory, Basic Rigging Workbook ↗ (accessed November 9, 2026)
- [8] OSHA, 29 CFR 1910.184, Slings ↗ (accessed November 9, 2026)
- [9] TRAK Machine Tools support, "TRAK TC820si & TRAK TC820LTYsi - Leveling" ↗ (accessed November 9, 2026)
- [10] Renishaw, "New life for worn machines" ↗ (accessed November 9, 2026)
Connect this question to the whole machine.
Machine ownership is a chain. Use the next relevant guide instead of treating any one checkpoint as the complete answer.
Research machinery movers
Compare published footprints and verify the actual crew and scope.
Open the guide →SHIPPINGResearch machine transport
Use carrier, heavy-haul and state permit resources.
Open the guide →ACCESSSurvey the last mile
Confirm the complete truck-to-foundation route.
Open the guide →Direct answers, with the boundary intact.
Machine Blue Book organizes research. It does not replace engineering, legal, tax, insurance, safety, appraisal or trade advice.
Does a freight quote usually include rigging?
Not necessarily. Define loading, unloading, final placement and every related service in writing.
Who obtains oversize permits?
The responsible applicant varies by arrangement and jurisdiction. Assign it and verify the issued authority before movement.
Is a certificate of insurance enough?
No. It is evidence of insurance, not the policy. Verify applicable coverage, limits, exclusions, insured entity and scope.
When should machine condition be documented?
Before disconnection, after preparation, at loading, delivery, unloading, placement and final acceptance as the project requires.
Do I need to relevel after every move?
Yes. A move changes how the machine sits on the floor; level it and check geometry each time.
Why are there no cost figures on this page?
The Machine Blue Book publishes research, not quotes. Get written quotes from riggers and compare the scope, not just the total.
Machine Buying Guide
Carry this evidence into the rest of the decision—from machine identity through handover and final economics.